Project: Sitka Lodge Expansion - Underground Mechanical Install and Site Gradework
Client: Civeo
General Contractor: Daudet Creek Contracting
Date: November 2018 to present
Contract: Lump Sum / Unit Price / Time & Materials
Value: $1,000,000 to 4,999,999
Scope: Supply and install sanitary sewer lines, manholes, water line (potable and firewater), electrical services and gas line for temporary camp, and 20-dorm expansion. Install compacted gravel bases, ramps, culverts, walkways and asphalt aprons for new dorms. Build delivery access road and fuel tank pad. Install 135,000L buried sanitary tank including connections and anchorage. On-site snow removal.