Supplied and installed 4200 m of partially insulated twin line force sewer main including emergency by-pass port, bends, in-line gate valves & air valve chambers, 40 sanitary service connections, 30 sanitary service tie-ins, 41 trenchless crossing tie-ins, terminal clean-out chambers, pressure sustaining valve chambers, 400 mm and 500 mm CSP culverts, and emergency by-pass ports. Some drilling and blasting of trench rock was required, as well as tree and shrub removal, aggregate import and lift station site grading. Milling, overlaying and tack coating as well as permanent pavement restoration was done on affected driveways, walkways and roadways.